Meeting solid preRD cher
From solidwiki
Contents
info
- entire TCD readout channel count table https://docs.google.com/spreadsheets/d/13URifVfeglIG4pA04JUWV7Ygb8fSg9Acx5bbL52leQ8
- DAQ and run info (give your redmine account to Alex for access) https://redmine.jlab.org/projects/telescope-cerenkov/wiki
- benchtest wiki Cherenkov_readout
meeting
Monday, January 27th, 2020
- Schedule update
- Tentative installation schedule: Beginning of March.
- Engineering status
- Ed and I will transport the tank to JLab on Thursday, we plan on being there in the early-mid afternoon.
- Tank and cradle is mostly finished.
- All BNC patch cables (150 8') are done, still need to finish ~30 SHV patch cables.
- Stand updates
- PMT and LAPPD coating is finished.
- Electronics update?
- Zhiwen tested the sum board, has ringing.
- DAQ status?
- Computer for data storage?
- Analyzer?
- Documentation
Monday, January 13th, 2020
- Engineering status
- Updates on Tank Construction
- Updates on Stand Construction
- Cabling update:
- About 100 8' BNC patch cables are done, still need to make 40-50 BNC and all the SHV:
- Do we need additional SHV patch for all scintillators and calorimeter PMTs. I have enough ends to make ~30 cables, but that will cover the MaPMTs + a few extras. I will need to order more SHV connectors if the lab doesn't have enough cables.
- Lemo cables? (DAQ side)
- Mirrors update:
- We have everything, just need to assemble
- Electronics board update:
- Have everything, sending the boards and 160 MCX connectors and PMT pin bases to JLab on Wednesday morning.
- I need to find out how long it will take to have a board assembled.
- Just ordered the LV cable (and connectors) needed to run up to 50'.
- Have everything, sending the boards and 160 MCX connectors and PMT pin bases to JLab on Wednesday morning.
- Tank delivery
- Still Monday the 20th?
- A1 is running well now! d2 change over "unofficially" delayed by 2 weeks.
- Electronics board and LV cable are the holding issues.
- Still Monday the 20th?
- DAQ
- Are we ready to set up a cosmics DAQ
- Computer purchase?
- Analyzer programing?
- Documentation for device
- Safety documentation for JLab
- Alignment, calibration, and commissioning procedures.
- Lasers to align to beam-line.
- Heavy gas fill procedure
- Environmental/safety issues with heavy gas purge?
- Run Plan
- Tentative order:
- Low rate / large angle with N2 and summing board
- Access will be for install, will need to repressurize.
- Low rate / large angle with N2 and LAPPD
- Access will be opportunistic, will need to repressurize.
- High rate / small angle with N2 and LAPPD
- Access needed to switch to small angle.
- High rate /small angle with N2 and summing board
- Access will be opportunistic, will need to repressurize.
- High rate /small angle with Heavy Gas and summing board
- Access will be opportunistic, will need to flush and fill with heavy gas.
- High rate /small angle with Heavy Gas and MAROC
- Access will be opportunistic, will need to refill with heavy gas.
- Low rate / large angle with N2 and summing board
- Tentative order:
- Kinematics switch timeline/plan
Monday, January 6th, 2020
- Any A1/d2n scheduling updates?
- Engineering status
- Updates on Tank Construction
- New cradle design with 80/20:
- LAPPD box has leaky BNC feed throughs. Not sure about MaPMT box.
- Updates on Stand Construction
- Updates on Tank Construction
- Outstanding items that need to be ordered/built/procured
- Status of current orders:
- MaPMTs (Ordered via ANL)
- Mirrors (ECI film shipped, expected today/tomorrow)
- Still need to do mirror assembly, i.e. attach film to carbon fiber blank. We have lexan film with no reflective coating to test.
- Electronic summing board board (Ordered, board is printed and currently in component assembly)
- Also will need to have MCX connectors attached (done at JLab, if Jack hasn't disowned us)
- Gas regulation system (In hand, being assembled)
- Cabling between prototype and patch-panel
- Cabling (Components are in hand and set up to make 150 8' BNC patch cables and ~30 patch SHV, construction this week)
- Do we have the additional SHV cables at the Lab?
- Cabling between patch-panel and DAQ
- Do we have the necessary BNC and SHV? Can we find the lemo cables? (Who to ask, Alex?)
- Status of current orders:
- Tank delivery estimate?
- Assuming 2-weeks from today (Jan 20th). If we are ready sooner, we will deliver ASAP.
- I'll likely be delivering the tank to JLab alone, so I will need some help loading and unloading the van.
- Assuming 2-weeks from today (Jan 20th). If we are ready sooner, we will deliver ASAP.
- Preparation of Cosmics test.
- Space at the lab?
- Electronics and cables ready?
- Schedule for bench testing calorimeter blocks and scintillators.
- Documentation for device
- Safety documentation for JLab
- Alignment, calibration, and commissioning procedures.
- Lasers to align to beam-line.
- Heavy gas fill procedure
- Run Plan
- Kinematics switch timeline/plan
Monday, December 16th, 2019
- Engineering status
- Updates on Tank Construction
- Updates on Stand Construction
- Outstanding items that need to be ordered/built/procured
- Status of current orders:
- MaPMTs (Need ordering institution)
- Mirrors (ECI film ordered)
- Electronic summing board board (Final quote determined, 2-week lead time)
- Gas regulation system (ordered, still needs to be assembled)
- What extra care do we need for gas tank, plumbing from tank on the floor to tank on table should bbe straight forward.
- Cabling before patch-panel
- What patch cables do we need? 134 BNC patch cables? Can we use cables from the previous prototype? How about SHV? Do we need 70 SHV patch cables also?
- Cabling after patch-panel
- Do we have the necessary BNC and SHV? Can we find the lemo cables? (Jian-Ping seems to think we can find the lemo cables at JLab)
- Status of current orders:
- Preparation of Cosmics test.
- Space at the lab?
- Electronics and cables ready?
- Schedule for bench testing calorimeter blocks and scintillators.
- MaPMT pixel test with wavelength shifter coating
- Documentation for device
- Status of SOW's for Argonne
- Safety documentation for JLab
- Alignment, calibration, and commissioning procedures.
- Lasers to align to beam-line.
- Heavy gas fill procedure
- Run Plan
- Kinematics switch timeline/plan
Monday, December 9th, 2019
List of topics for meeting today:
- Engineering status
- Updates on Tank Construction
- Is there adequate space in the current design for the scintillator arrays? Image of Design
- Updates on Stand Construction
- Updates on Tank Construction
- Outstanding items that need to be ordered/built/procured
- Status of current orders:
- MaPMTs
- Mirrors
- Electronic summing board board
- Use MCX connectors with MCX to BNC conversion cables? $2400 total cost on entire MCX to BNC out, saves time on assembly/labor.
- MAROC electronics
- Gas regulation system
- Status of lead block availability at JLab?
- Status of lemo cable availability at JLab?
- Status of BNC cable availability at JLab?
- Status of SHV cable availability at JLab?
- Status of current orders:
- Preparation of Cosmics test.
- Space at the lab?
- Electronics and cables ready?
- Schedule for bench testing calorimeter blocks and scintillators.
- MaPMT pixel test with wavelength shifter coating
- Documentation for device
- Status of SOW's for Argonne
- Safety documentation for JLab
- Alignment, calibration, and commissioning procedures.
- Heavy gas fill procedure
- Run Plan
- Kinematics switch timeline/plan
Monday, November 11th, 2017
- Some design pictures from Ed are below: