Weekly : Monday, May.28, 2019 11:00am EDT
From solidwiki
Agenda
- Discussion on SoLID cost estimation according to WBS (Work Breakdown
Structure)
- Sub-system updates
Minutes
- JP: Thanks for every to get those cost estimation tables done last week. Except DAQ system from Alexandre, what's the slow control cost?
- Alexandre: will add that part.
- JP: We need the start and end time, and how long it takes for each item. We want to have enough information and documents for the cost direct review. Possibly we will start on FY2023 (October 1, 2022).
- Xiaochao: Need to define a better name for ECAL support.
Present
Alexandre, JP, Ole, Paul, Nilanga, Michael, Robin, Whit, Xiaochao, Stephen, Jinglong, Ye, Rich, and Zhiwen